40-Year Recertification in Miami-Dade: A Timeline Memo for North Miami Beach Condo Boards and Owners

To: condo and co-op boards, property managers and owners in North Miami Beach.
Re: what "40-year recertification" means now, and the dates that matter.
Many people still say "40-year recertification," but in Miami-Dade the rule has moved. Since June 2022 the County's trigger is earlier for most buildings, and since 2022 Florida has layered its own milestone inspection and reserve study requirements on top. This memo sorts out which rule applies to your building, in the order a board will run into them.
1. Who sends the notice in North Miami Beach
Recertification is a Miami-Dade County program under County Code Section 8-11(f), but in North Miami Beach the reports go to the City's Building Department, Governmental Compliance Section. The City's Recertification page describes the program and links the forms. The Building Department is at 17050 NE 19th Ave, 305-948-2965.
2. When your building is due
From Miami-Dade's recertification page:
| Building | First recertification | After that |
|---|---|---|
| Built 1982 or earlier, already recertified | Continues on its existing cycle | Every 10 years |
| Built 1983–1992 | Was due by December 31, 2024 | Every 10 years |
| Coastal condo/co-op, 3+ stories, built 1983–1997 | Was due by December 31, 2024 | Every 10 years |
| Coastal condo/co-op (within 3 miles of the coastline), 3+ stories, built 1998 or later | At 25 years | Every 10 years |
| All other buildings built 1993 or later | At 30 years | Every 10 years |
Exempt: single-family homes, duplexes, and minor buildings with 10 or fewer occupants and 2,000 square feet or less. Much of North Miami Beach sits near the Intracoastal and the ocean, so many of its condo buildings may fall inside the 3-mile coastal band. Confirm your building's status with the City.

3. What the reports are
A Florida-registered engineer or architect inspects and prepares structural and electrical reports. Threshold buildings, generally four stories and up, need separate structural and electrical engineers. The reports confirm the building is safe for continued use, or identify repairs.
4. The County clock
- 90 days from the notice to submit the reports.
- A 60-day extension is available for a fee ($75.58 on the County's current schedule).
- The County lists an initial review fee of $403.13 and a late fee of $453.52, under fee changes effective October 1, 2025.
- Non-compliance can bring a $510 citation, penalties up to $10,000 per violation, and liens.
Those figures are from the County program. North Miami Beach administers recertification locally, so confirm its fees and deadlines with the City's Governmental Compliance Section.
5. The state milestone inspection (F.S. 553.899)
After the Surfside collapse, Florida added milestone inspections for condo and co-op buildings with three or more habitable stories. Under F.S. 553.899, as amended through 2025:
- The inspection is due by December 31 of the year the building turns 30, then every 10 years.
- Local agencies may set 25 years based on local conditions such as proximity to salt water. Miami-Dade uses 25 years within 3 miles of the coast.
- Phase 1 is a visual inspection, due within 180 days of the local agency's certified-mail notice.
- Phase 2 is required if Phase 1 finds substantial structural deterioration, with a progress report due within 180 days.
- The association must notify owners within 14 days of receiving the notice, and send the inspection summary within 45 days of receiving it.
- Repairs must start within 365 days of the Phase 2 report, or the building official decides whether the building is unsafe to occupy.
In practice, Miami-Dade buildings coordinate the County recertification and the state milestone inspection. Ask your engineer how they'll handle both.

6. The reserve study (SIRS)
The second post-Surfside requirement is the structural integrity reserve study (SIRS) under F.S. 718.112(2)(g), for condo buildings three or more habitable stories, every 10 years. The statute in force in 2026 provides:
- The first SIRS was due by December 31, 2025. It can be combined with a milestone inspection due by December 31, 2026, but in no event later than December 31, 2026.
- It covers the roof, structure, fireproofing and fire protection, plumbing, electrical, waterproofing and exterior paint, windows and exterior doors, and any other item costing more than $25,000 (inflation-adjusted).
- Associations can't waive reserves for these items in budgets adopted on or after December 31, 2024.
- After a milestone inspection, owners may pause or reduce reserves for up to two budgets, through budgets adopted by December 31, 2028, so the money can go to the repairs.
7. The board's working timeline
- Now: confirm your building's construction year and whether it's within 3 miles of the coast. Check the City's records for prior recertifications.
- Before the notice: get engineer proposals. Good firms book up, especially as large groups of buildings come due together.
- Notice arrives: notify owners within 14 days and start the 90-day County clock.
- Inspection: make sure inspectors can reach everything. That means clearing storage rooms, electrical rooms, roof access and garages.
- Reports filed: distribute the summary, budget the repairs, and update the SIRS.
- Repairs: permits, contractor schedule, resident communication. Start within 365 days if Phase 2 found deterioration.

8. The part nobody budgets for: access and debris
Recertification and milestone work keeps running into a practical problem: stuff in the way. Inspectors need to see walls, slabs and electrical gear. Concrete restoration crews need clear balconies, garages and units. Storage cages and common rooms that collected decades of abandoned items have to be emptied first.
Then the repairs themselves produce construction debris: old railings, drywall, tile and concrete. North Miami Beach's bulk pickup doesn't take construction debris, and buildings with five or more units deal with Coastal Waste & Recycling directly. Plan disposal into the repair contract or line up a hauler.
Questions owners should ask the board
- When is our building's next recertification or milestone inspection due, and has the engineer been hired?
- Did the last inspection find anything that requires Phase 2 work?
- Is our SIRS complete, and what does it say about reserves for the roof, structure and waterproofing?
- Will repairs require access to individual units or balconies, and when?
- Is a special assessment likely, and how will it be scheduled?
Boards that answer these early get far fewer angry calls later.
9. If the building is found unsafe
When a building official finds a structure unsafe, the matter can go before an unsafe structures process. Miami-Dade County's Unsafe Structures Board reviews Building Official decisions for the County. Ask the City Building Department how North Miami Beach handles unsafe-structure cases. The goal of the whole system is to fix problems long before that point.
Where Junk Ranger fits
We don't do inspections or structural repairs. We clear the way for them. Junk Ranger Removal handles condo cleanouts, common-area and storage cleanouts, and construction debris removal during restoration work across North Miami Beach, Aventura and Sunny Isles Beach. Our guide to Florida condo rules for cleanouts and renovations covers working within association rules.

Frequently asked questions
Is it still called 40-year recertification in Miami-Dade?
Who handles recertification in North Miami Beach?
Are single-family homes subject to recertification?
How long do I have to file recertification reports in Miami-Dade?
What is a milestone inspection in Florida?
What is a SIRS?
What happens if a condo misses recertification?
Keep reading
- Florida Condo Rules That Affect Cleanouts and Renovations
- North Miami Beach Building Department: A Permit Checklist for Demolition and Renovation
- Clearing a Florida Condo After a Death: Rules Nobody Warns You About
- All junk removal and demolition services in North Miami Beach

Junk Ranger Removal is a licensed and insured junk removal, cleanout and demolition crew serving North Miami Beach, Miami-Dade County and all of Florida. Free estimates: (561) 699-0121 · estimates@junkrangerremoval.com · Junk removal in North Miami Beach